Organization
- Principle investigator: Prof. Michel Mayor, Observatoire de Genève
- Co-Investigators:
- Prof. Willy Benz, Universität Bern
- Dr. Jean-Loup Bertaux, Service d'Aéronomie
- Dr. Jean-Pierre Sivan, Observatoire de Haute-Provence
- Project Scientist: Dr. Didier Queloz, Observatoire de Genève
- Instrument Scientist ESO: Dr. Luca Pasquini, ESO Garching
- Project Manager: Dr. Francesco Pepe, Observatoire de Genève
- Responsible System Engineer ESO: Dr. Gero Rupprecht, ESO Garching
- Responsible Project Manager La Silla: Dr. Ueli Weilenmann, ESO La Silla
- SW Manager: Dr. Denis Mégevand, Observatoire de Genève
Involved institutes
- Customer: ESO
- Contractor: HARPS Consortium
Milestones
Milestones |
From KO |
Date |
Site |
BDR |
T0 - 13 months |
26 January 1999 |
Geneva |
KO |
T0 |
February 2000 |
Geneva |
FDR Optics |
T0 + 2 months |
6th and 7th April 2000 |
OHP |
PDR |
T0 + 5 months |
11th and 12th July 2000 |
Garching |
PDR SW |
T0 + 10 months |
18th December 2000 |
Geneva |
FDR |
T0 + 13 months |
28th and 29th March 2001 |
Garching |
FDR SW |
T0 + 17 months |
2nd July 2001 |
Geneva |
PAE |
T0 + 33 months |
24th November 2002 |
Geneva |
PAC |
T0 + 43 months |
September 2003 |
La Silla |
FAC |
T0 + 103 months |
September 2008 |
Garching |
[ Planet Group
| Geneva Observatory
| University of Geneva
| ESO]
Last changed: Monday, 16-Jun-2003 16:15:47 CEST
Danuta Sosnowska - Copyright ©