VLTI

The PRIMA DDL-AOS Project
Milestones

Milestones Date Site
Proposal to ESO/BDR September 2003 Garching
OK by ESO Council for DDLs December 2003 Garching
DDL Kick-Off Meeting 12 February 2004 Geneva
Revised AOS proposal to ESO April 2004 Garching
OK by ESO Council for AOS June 2004 Garching
AOS Kick-Off Meeting 23 June 2004 Glasgow
AOS Preliminary Design Review 27 June 2005 Garching
DDL Preliminary Design Review 29 June 2005 Garching
DDL SW Preliminary Design Review 19 October 2005 Geneva
DDL Final Design Review 3, 4 July 2006 Garching
DDL CS Final Design Review 6, 7 November 2006 Geneva
AOS Final Design Review 2, 3 April 2007 Garching
Optics Acceptance Meeting October 2007 Heidelberg
AOS Intergration Readiness Meeting April 2008 TBD
DDL Provisional Acceptance Europe February 2008 Geneva
AOS Provisional Acceptance Europe May 2008 Heidelberg
DDL Provisional Acceptance Chile July 2008 TBD
AOS Provisional Acceptance Chile August 2008 TBD
Astrometry Commissioning August 2008 Paranal
DDL Final Acceptance Chile DDL-PAC + 2 years Garching
AOS Final Acceptance Chile AOS-PAC + 3 years Garching