The PRIMA DDL-AOS Project Milestones |
Milestones | Date | Site |
Proposal to ESO/BDR | September 2003 | Garching |
OK by ESO Council for DDLs | December 2003 | Garching |
DDL Kick-Off Meeting | 12 February 2004 | Geneva |
Revised AOS proposal to ESO | April 2004 | Garching |
OK by ESO Council for AOS | June 2004 | Garching |
AOS Kick-Off Meeting | 23 June 2004 | Glasgow |
AOS Preliminary Design Review | 27 June 2005 | Garching |
DDL Preliminary Design Review | 29 June 2005 | Garching |
DDL SW Preliminary Design Review | 19 October 2005 | Geneva |
DDL Final Design Review | 3, 4 July 2006 | Garching |
DDL CS Final Design Review | 6, 7 November 2006 | Geneva |
AOS Final Design Review | 2, 3 April 2007 | Garching |
Optics Acceptance Meeting | October 2007 | Heidelberg |
AOS Intergration Readiness Meeting | April 2008 | TBD |
DDL Provisional Acceptance Europe | February 2008 | Geneva |
AOS Provisional Acceptance Europe | May 2008 | Heidelberg |
DDL Provisional Acceptance Chile | July 2008 | TBD |
AOS Provisional Acceptance Chile | August 2008 | TBD |
Astrometry Commissioning | August 2008 | Paranal |
DDL Final Acceptance Chile | DDL-PAC + 2 years | Garching |
AOS Final Acceptance Chile | AOS-PAC + 3 years | Garching |