Paranal Mission 19

Loading Map....

Date/Time
Date(s) - 11/08/2017 - 19/08/2017
All Day

Location
Paranal Observatory

Categories


 

 

This mission intended to prepare the CCL with hard work for the further installation missions of the electronics rack and cables.
Drilling was performed in the ceiling and floor of the 1T and cabinets room, apertures were cut in the 2T walls.

Attendees

Nigel Evershed
Gaspare Lo Curto
Denis Mégevand
… and Paranal staff

 

            Opened apertures in the niche and 2T walls

 

 

 

 

 

Drilled the floor and install racks damper for FE and general cabinets

 

 

 

 

 

 

 

 

 

Installed the FEU cabinets cooling distribution panel with Eloy Fuenteseca

Created an airlock to enter 2T

 

See full report document VLT-MIN-ESP-13520-0258