The following check-list is intended as a guide-line for Coralie Observers. Of course the detailed sequence of the various task can be modified. This list shall just help in reminding these general steps. For discussion on observing strategy please contact the Coralie Group or refer to the document “Coralie pour les Nuls” to be found on the T4 web page.
1. Check the water level in the two humidifier and refill if necessary
2. If you burned CDROMs or DVDROMs, check their status and stock Master and
COPY CD in respective boxes. If you put the data of the preceding night(s) on
USB, check the integrity of the data.
3. Check Coralie and Camera temperature whether “OK”
4. Check the Coralie-dewar (TP-60) LN2-level.
5. Check the Camera-dewar (Ranger) LN2-level
6. Archive the data, either on CD, DVD or USB disk. Use for this purpose
the Data Archiving Unit (DAU). Type “dau.csh” in a terminal and a user
interface will appear. Create one CD/DVD for the La Silla local archive and put
it in the box on the right desk (write the night date, ‘CORALIE’ and ‘MASTER’
on it), and create either one CD/DVD for your institution or put the data on
your USB disk.
7. Start-up instrument without telescope
8. Login on Castor from the terminal “t4main”
9. Login on Castor1, e.g from the
terminal “t4aux-left”
10.Insert standard calibration
exposures (“insert calib”) into the edp and start the calibrations (“Lancer une pose” in “UIF Coralie”). Put an “Auto Stop” after the
calibration exposure in order to avoid that the observation start too early.
11.Refill the Caméra 2 with LN2 following
the procedure
12.Open the dome windows
13.Prepare your observation night in “edp”,
e.g. by loading the sources from a catalogue.
14.When the filling tube is warm,
disconnect it from the C2 camera put the filling tube back in its park
position. Make sure that the security switch is off (red led is off)
15.After the end of the calibration
exposures start-up the telescope in the xrunall panel: “Démarrage du télescope”
16.Report possible errors during the
start-up via the problem-report
web page
17.Open the dome with the command
“Ouverture de la coupole” in the xrunall panel
18.Close the curtains to avoid stray light.
19.Start the observation night perform the
observations (“Lancer une pose” in “UIF Coralie”)
20.Wait the end of the reduction and make a
“Fin de nuit”
21.Connect tube to the C2 camera and start
a LN2 re-filling of the Caméra 2
22.Close the windows inside the dome
23.Put on TEUPS AES BCO
button on "Hors" position
24.Put on TEUPS
Raquettes TE button on "Hors" position
25.Go to bed and sleep
well, but before close the building door